Locker Rooms | What Do You Need?

“The Map” Dates

< All Topics
Table of Contents

Preparation for January:

December 1-3 -FB/ Google Spend entered

December 4 -GG schedule meeting to review projections

December 4-8- GG meet and sign off

December 9- Buyer copy over projections to kpi doc

December 10-11-FB/ Google Manager Sign off

December 14-15 -Aaron/ Chris/ Scott sign off

December 16-18-GG lock in targets with client

Preparation for December:

November 10-13 -FB Spend entered

November 13-16 -Google Spend entered

November 13- GG schedule meeting to review projections November 17-19 GG meet and sign off 


November 20- Buyer copy over projections to kpi doc November 20-23 FB/ Google Manager Sign Off


November 24-25 Aaron/ Chris/ Scott sign off

November 26-30 -GG lock in targets with client

Preparation for November:

October 16 – Buyer Bottom-up budget due


October 19 – Growth Guides QA Forecast


October 21 -23 Manager Forecast Review and Approval Meetings. 


October 26-29 – Growth Guide Map Meeting

Oct 30 – Approval Due from the Client + KPI sheet is updated.


Preparation for October:

Sept 18 – Buyer Bottom-up budget due


Sept 21 – Growth Guides QA Forecast


Sept 23-25 – Manager Forecast Review and Approval Meetings. 


Sept 25 – Final Version of Plan Due to Manager


Sept 30 – Approval Due from the Client + KPI sheet is updated.